Approved Gryphon programme removes the FPSO and leaves its wells for later

The High Court dismissed a field partner's challenge in August 2025; the programme covers vessel removal, with plugging and subsea work still to come.

Date
Reading time
2 min

Written with AI tools by EM Governance Review's editorial system; the publisher is responsible for it. How this site works

Cover card: UK decommissioning, Gryphon wells wait for a later programme

The High Court dismissed the first judicial review brought by a part-owner of the Gryphon FPSO decommissioning and refused permission for the second on 12 August 2025, the judgment shows; the final programme for removing the vessel was issued on 28 August 2025.

The claimant, Nobel Oil E&P North Sea Limited, holds an interest of around 8 per cent in each of the Maclure and Ballindalloch fields tied back to the floating production, storage and offloading vessel, which TotalEnergies operates. The first review challenged the North Sea Transition Authority's advice to the operator under section 29 of the Petroleum Act 1998; the second challenged its advice to the Offshore Petroleum Regulator for Environment and Decommissioning (OPRED) under section 32. Mr Justice Dove concluded that neither application "can properly succeed on the merits", dismissing the first and refusing permission for the second. Lord Justice Males agreed.

Gryphon fields: wells by status in the final decommissioning programmewells
Source: TotalEnergies E&P North Sea UK Limited, Gryphon Alpha FPSO and Riser Disconnection Decommissioning Programmes, final issue, 28 August 2025

The claimant relied on six grounds in the first review, among them predetermination and apparent bias, procedural unfairness and a breach of the Tameside duty to inquire. The court recorded that the vessel was built in 1993, refurbished after a major incident in 2012 and recertified to 15 November 2027, and that the claimant challenged support for cessation of production at the end of 2024. Lord Justice Males said it was rational for the regulator to conclude that accelerated cessation was consistent with maximising economic recovery of UK petroleum, because the remaining oil reserves were relatively modest and the vessel was an ageing facility vulnerable to breakdown.

The final decommissioning programmes, issued on 28 August 2025 with TotalEnergies E&P North Sea UK Limited as operator, cover Phase 1 only. That phase is the full removal of the vessel, its flexible risers, dynamic umbilicals, mooring lines and anchors from Block 9/18b, about 169 km southeast of Shetland in around 112 m of water. The programme names the operator (86.5 per cent) and Sojitz Energy Development Limited (13.5 per cent) as the installation's section 29 notice holders, and planned sail-away for the third or fourth quarter of 2025. The pipeline sections covered total 17 pipelines and 5.412 km.

The wells stay for later. The programme lists 26 production wells, 1 gas injection well and 5 water injection wells across the connected fields, with a further three wells abandoned to the AB1 stage awaiting AB3 and 14 shut in awaiting abandonment. It says none will be decommissioned at this time. Phase 2, well plugging and abandonment, and Phase 3, subsea installations and pipelines, will have separate programmes, with the earliest field-wide plugging campaign estimated to start in 2026, subject to studies, tenders and rig or vessel availability, and the earliest execution of the multi-year well campaign in 2026 or 2027.

The consultation record in Appendix 2 includes a letter dated 18 October 2024 from the claimant's group, which trades as Nobel Upstream, and the operator's responses to it. The sources reviewed do not confirm that the planned sail-away took place, show the later programmes or record an appeal. Carbon costs feature in the reasoning, as Lord Justice Males said the regulator was entitled to take societal carbon costs into account; for a market building its own carbon price, see our report on Türkiye's emissions trading pilot, and for the investor-state route for resource disputes, our Arbitration Watch.

Authorities

2 sources, all primary

  1. Nobel Oil E&P North Sea Limited, R (on the application of) v The Oil and Gas Authority t/a The North Sea Transition Authority & Ors [2025] EWHC 2139 (Admin) (Nobel Upstream group)High Court of Justice (Administrative Court), via The National Archives, Primary source, 12 August 2025
  2. Gryphon Alpha FPSO and Riser Disconnection Decommissioning Programmes, final issueTotalEnergies E&P North Sea UK Limited, published by GOV.UK (OPRED), Primary source, 28 August 2025